Year:
      2008
Location:

      Tehran-Iran
Client:
      T.O.R.C (Tehran Oil Refining Company)
Contractor:
      Barsan Co.
Plant Specification:
      Compressors in Isomax and Catalytic reformer units
Our Scope of work:
      Control system & instrumentation design, fabrication, commissioning and startup
Hardware:

      SIEMENS PLC S7-315 2DP (Redundant CPU included two racks I/O module) and two OP 270 (Operator Panel)
Architecture & IO Quantity:
     • 6 sets of Compressor control panels & 12 HMI devices & Instrumentation
Software Specification:
     • STEP7
     • WinCC Flexible