Year:
      2012-2013
Location:

      Gotvand-Iran
Client:
       IWPC (Iran Water & Power Resources Dev. Co.)
Contractor:
       ALSTOM
Plant Specification:
       4x250 MW Hydroelectric Power Plant
Our Scope of work:
       Unit Control & Protection system commissioning and startup
Hardware:
       ALSPA P320 (Redundant PCX control system including two sets of PLC)
Architecture & IO Quantity:
     • 4 sets of Unit control panels & local HMI
     • 4 sets of protection panels
     • Auxiliary control panel
     • Common PLC and SCADA control panel
     • DAM control panel
     • S8000 redundant optical fiber
Software Specification:
     • Two redundant Centralog stations
     • One historian server
     • One Large screen display (4 LSD)